During initial construction it became evident that the remaining part of the circuit required more attention to drivers' and spectators' safety, says track engineers. After an inspection it was decided to replace all debris fencing, safety barriers and tyre and belting safety systems around the entire circuit. The decision was also taken to replace all gravel in the arrester beds and, after consultation with the International Automobile Federation, tarred run-off areas have been added at Sunset and Ingwe corners. More than 60km of cable has been ordered for the new-specification debris fencing that will be erected around the circuit. Owing to the increase in the scope of works the completion date for the track project is expected to be towards the end of October 2015.